In the Determine Budget processes the project schedule
Correct Answer: is used to assign costs to the time period when the costs will be incurred
Explanation:
“This [project schedule] information can be used to aggregate costs to the calendar periods when the costs are planned to be incurred.” PMBOK [7.2.1.4]