Correct Answer: Earned Value(EV) divided by Planned Value (PV)
Explanation:
Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it’s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance.