In critical chain project management, which of the following is not typically recognized as a buffer type used to protect the schedule?

Difficulty: Medium

Correct Answer: Free buffer.

Explanation:


Introduction / Context:
Critical chain project management (CCPM) is a schedule focused methodology that emphasizes resource constraints and the use of buffers to protect the project completion date. Understanding the different buffer types is an important exam topic. Typical buffers include project buffers, feeding buffers, and resource buffers. The question asks you to identify which listed type is not normally recognized as a buffer in critical chain scheduling.


Given Data / Assumptions:

  • We are working within the CCPM framework, which builds on critical path concepts but adds resource considerations.
  • Common buffers in CCPM include project buffer, feeding buffer, and resource buffer.
  • One option, free buffer, sounds similar to free float but is not a standard CCPM buffer type.
  • The question requires distinguishing CCPM terminology from related but different schedule concepts.


Concept / Approach:
In CCPM, the project buffer is placed at the end of the critical chain to protect the overall completion date. Feeding buffers are inserted where non critical chains feed into the critical chain to protect it from delays on those paths. Resource buffers are alerts or time buffers placed before critical resource activities to ensure resources are available when needed. The term free buffer is not standard; the similar term free float is used in traditional critical path method scheduling to describe how much a task can slip without affecting subsequent tasks. Therefore, recognizing free buffer as the odd term is the key to answering correctly.


Step-by-Step Solution:
Step 1: List the known CCPM buffer types: project buffer, feeding buffer, and resource buffer. Step 2: Compare these known types to the answer choices and identify which ones match. Step 3: Note that free buffer does not appear in CCPM literature, while free float does appear in traditional critical path discussions. Step 4: Conclude that free buffer is the term not typically recognized as a CCPM buffer type.


Verification / Alternative check:
If you review CCPM references, you will consistently see explanations about project buffer at the end of the critical chain, feeding buffers on non critical feeding paths, and resource buffers to manage resource availability. None of these references introduce the term free buffer. Meanwhile, project scheduling textbooks discuss free float and total float, which are not called buffers in CCPM terminology. This comparison confirms that free buffer is not a standard buffer type in critical chain management.


Why Other Options Are Wrong:
Option B, resource buffer, is a recognized CCPM concept used to warn resources of upcoming work. Option C, project buffer, is central to CCPM and protects the overall project completion date from variance on the critical chain. Option D, feeding buffer, protects the critical chain from delays on non critical paths that feed into it. Since all of these are valid CCPM buffer types, they cannot be the correct answer to a question asking which one is not a typical buffer type.


Common Pitfalls:
A frequent pitfall is confusing float terminology from critical path method with buffer terminology from CCPM. Some learners see the word buffer and assume it matches free float or total float, but CCPM deliberately uses different terms and concepts. Another mistake is assuming that any familiar scheduling term is part of every methodology, which can lead to incorrect associations on exam questions. Carefully distinguishing between CCPM buffers and CPM float types is important for exam success.


Final Answer:
The term that is not typically recognized as a CCPM buffer type is free buffer.