Difficulty: Medium
Correct Answer: 30
Explanation:
Introduction / Context:This is a classic “planned strength vs. actual strength” time and work problem. We equate total work using rate * time with different crew sizes.
Given Data / Assumptions:
Concept / Approach:Let a single man’s daily rate be r. Total work W can be written two ways and equated.
Step-by-Step Solution:
Planned work: W = M * r * 18Actual work: W = (M − 12) * r * 30Equate: M * 18 = (M − 12) * 3018M = 30M − 360 ⇒ 12M = 360 ⇒ M = 30Verification / Alternative check:Plug back: Planned capacity per day = 30r; in 18 days gives 540r. Actual capacity per day = 18r; in 30 days gives 540r. Matches.
Why Other Options Are Wrong:
Common Pitfalls:Forgetting to hold total work constant or mixing up which team size applies to which duration.
Final Answer:30
Discussion & Comments