Comparing speeds to infer joint time A is three times as efficient as B and thus completes the job 30 days sooner than B. In how many days will A and B finish the job working together from start to finish?

Difficulty: Medium

Correct Answer: 45/4 days

Explanation:

Introduction / Context:The problem gives a relative efficiency (A is 3x B) and a difference in their individual completion times (A finishes 30 days sooner). From this, we can find individual times and then the joint time.

Given Data / Assumptions:

  • A is three times as efficient as B.
  • A needs 30 fewer days than B to complete the job alone.

Concept / Approach:If B alone takes t days, then A alone takes t/3 days (because A is 3x as fast). The difference t − t/3 = 30 allows solving for t. Then combine rates.

Step-by-Step Solution:

t − t/3 = 30 ⇒ (2/3)t = 30 ⇒ t = 45 days (B’s time)A’s time = 45/3 = 15 daysJoint rate = 1/15 + 1/45 = 4/60 = 1/15 + 1/45 = 4/45Joint time = 1 / (4/45) = 45/4 days = 11.25 days

Verification / Alternative check:In 11.25 days, A contributes 11.25/15 = 0.75 of the job, B contributes 11.25/45 = 0.25, totaling 1 job.

Why Other Options Are Wrong:15 days is A-alone time, not joint. 45/5 (=9) and 12 days do not match the combined rate.

Common Pitfalls:Equating “3 times as efficient” with “30 days less” without forming equations, or adding times instead of rates.

Final Answer:45/4 days

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion