Difficulty: Medium
Correct Answer: 45/4 days
Explanation:
Introduction / Context:
The problem gives a relative efficiency (A is 3x B) and a difference in their individual completion times (A finishes 30 days sooner). From this, we can find individual times and then the joint time.
Given Data / Assumptions:
Concept / Approach:
If B alone takes t days, then A alone takes t/3 days (because A is 3x as fast). The difference t − t/3 = 30 allows solving for t. Then combine rates.
Step-by-Step Solution:
Verification / Alternative check:
In 11.25 days, A contributes 11.25/15 = 0.75 of the job, B contributes 11.25/45 = 0.25, totaling 1 job.
Why Other Options Are Wrong:
15 days is A-alone time, not joint. 45/5 (=9) and 12 days do not match the combined rate.
Common Pitfalls:
Equating “3 times as efficient” with “30 days less” without forming equations, or adding times instead of rates.
Final Answer:
45/4 days
Discussion & Comments