Difficulty: Easy
Correct Answer: 36 days
Explanation:
Introduction / Context:This problem leverages the ratio of efficiencies. If A is 2 times as efficient as B, A’s rate is double B’s rate. From the joint time we can extract each individual time.
Given Data / Assumptions:
Concept / Approach:If B’s rate is b, A’s rate is 2b. Together rate = 3b = 1/12 ⇒ b = 1/36.
Step-by-Step Solution:
Let B’s rate = bA’s rate = 2bTogether: 2b + b = 3b = 1/12 ⇒ b = 1/36Therefore, B alone takes 1 / b = 36 daysVerification / Alternative check:Check rates: A = 2/36 = 1/18; B = 1/36; Together = 1/18 + 1/36 = 3/36 = 1/12.
Why Other Options Are Wrong:24, 18, 12 are not consistent with the 3b = 1/12 relationship.
Common Pitfalls:Confusing “2 times as efficient” with “2 days less” or miscomputing sum of rates.
Final Answer:36 days
Discussion & Comments