Concrete workability guideline: what slump range (in mm) is typically recommended for placing reinforced concrete in beams and slabs?
-
A25 to 50 mm
-
B25 to 75 mm
-
C30 to 125 mm
-
D50 to 100 mm
-
Enone of these
Answer
Correct Answer: 25 to 75 mm
Explanation
Introduction / Context:Slump is a quick measure of concrete workability. For beams and slabs, adequate workability eases placement and compaction without segregation, ensuring cover and finish quality.
Given Data / Assumptions:
- Normal reinforced concrete using conventional vibration.
- Ambient conditions are typical; no special admixtures like SCC assumed.
- Recommended slump ranges are those widely used in site practice and teaching references.
Concept / Approach:Beams and slabs generally require medium workability. A slump of about 25–75 mm is commonly recommended for reinforced sections placed with needle vibrators. Higher slumps may be used with plasticizers but risk segregation if not controlled; very low slumps hamper compaction around reinforcement.
Step-by-Step Solution:Identify member type: beams and slabs → medium workability.Select standard range → 25 to 75 mm.
Verification / Alternative check:Site method statements and handbooks list 25–75 mm for RCC beams/slabs, 75–100 mm for columns/walls where flow around congested bars is needed.
Why Other Options Are Wrong:
- 25–50 mm: on the leaner side; may be acceptable but lower bound of common practice.
- 50–100 mm or 30–125 mm: higher workability ranges more typical for heavily reinforced members or with admixtures; not the standard teaching answer.
- None of these: incorrect because 25–75 mm is appropriate.
Common Pitfalls:
- Using high slump without admixtures, leading to segregation and bleeding.
Final Answer:25 to 75 mm