For exposed concrete surfaces, what is the minimum duration of moist curing typically specified to achieve adequate early hydration and durability?
-
A3 days
-
B5 days
-
C7 days
-
D14 days
-
E10 days
Answer
Correct Answer: 7 days
Explanation
Introduction / Context:Proper curing maintains moisture and temperature to support cement hydration, reduce plastic shrinkage cracking, and improve durability. For exposed surfaces, inadequate curing leads to a weak, porous skin and higher permeability, undermining long-term performance.
Given Data / Assumptions:
- Surface type: exposed concrete (not permanently protected).
- Objective: select the minimum moist curing period commonly required.
- Assume ordinary Portland cement without special accelerators or hot-weather adjustments.
Concept / Approach:
Baseline prescriptions for OPC concretes specify not less than about 7 days of continuous moist curing for exposed surfaces. Longer periods (10–14 days) are recommended for blended cements or harsh climates, but the minimum benchmark remains 7 days for standard conditions.
Step-by-Step Solution:
Identify standard minimum curing for OPC → 7 days.Recognize that supplementary cementitious materials may warrant ≥10 days; however, the question asks the minimum.Choose 7 days accordingly.Verification / Alternative check:
Field QA often checks curing records and surface temperature/humidity; achieving 7 continuous days significantly improves near-surface strength and permeability versus shorter durations.
Why Other Options Are Wrong:
- 3 or 5 days: Too short for reliable hydration and durability gains.
- 14 days: Beneficial but beyond the asked minimum.
- 10 days: Typical for blended cements; not the baseline minimum for OPC.
Common Pitfalls:
- Stopping curing early due to schedule pressure, leading to dusting or map cracking.
- Counting intermittent wetting as continuous curing; continuity matters.
Final Answer:
7 days