The camber on pavements, is provided by
straight line method
parabolic method
straight line and parabolic at crown
elliptical method
circular method.
Correct Answer:
straight line and parabolic at crown
← Previous Question
Next Question→
More Questions from
Highway Engineering
Roadway width for a National highways and State highways (two-lanes) is
In complex situations, total time required for a driver to form a judgement and to act, may be taken as
Ruling gradient on hill roads 300 m above M.S.L. is kept
The ratio of maximum deviation angle and maximum polar deflection angle of a Lemniscate curve, is
The length of a transition curve, is governed by
Pick up the incorrect statement from the following. On highways circular curves may be
The minimum cross fall of shoulders is kept
Thickness of broken centre line markings for a four lane road, is generally kept
In welded wire mesh, the longitudinal wire is placed at
Along a hill road, a side drain is provided on
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments