Pick up the incorrect statement from the following:
Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil
The lead is calculated for each block of the excavated area
The unit of lead is 50 m for a distance upto 500 m
The unit of lead is 1 km where the lead exceeds 2 km.
Correct Answer:
The unit of lead is 1 km where the lead exceeds 2 km.
← Previous Question
Next Question→
More Questions from
Estimating and Costing
The expected out turn for earth work in excavation in ordinary soil per mazdoor per day is
The unit of measurement is per quintal for the following:
For the construction of buildings, the subheads of the estimate are
The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is
The weight of an item is measured correct to nearest
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments