Home » Civil Engineering » Construction Management

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is

Correct Answer: 25

← Previous Question Next Question→

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion