Difficulty: Easy
Correct Answer: 7.5 cm
Explanation:
Introduction / Context:
Vibration greatly assists compaction; therefore, very high slump is unnecessary and may cause defects. Selecting an appropriate slump prevents segregation and bleeding.
Given Data / Assumptions:
Concept / Approach:
Guides recommend a slump range of about 25–75 mm when vibration is applied. The upper bound 75 mm (7.5 cm) limits the risk of loss of cohesion under vibratory action.
Step-by-Step Solution:
Acceptable slump band under vibration ≈ 25–75 mm.Therefore maximum recommended slump ≈ 7.5 cm.
Verification / Alternative check:
IS 456 and site best practices align with the 25–75 mm recommendation for vibrated concrete.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
7.5 cm