Difficulty: Easy
Correct Answer: all the above
Explanation:
Introduction / Context:
Accurate water–cement ratio control demands predictable aggregate moisture. Poor stockpile practices cause random moisture swings, leading to inconsistent workability and strength.
Given Data / Assumptions:
Concept / Approach:
Large plan area and limited height reduce internal drainage gradients; avoiding cone piles minimizes moisture stratification; a 24-hour stand time lets moisture equalize throughout the pile.
Step-by-Step Solution:
Adopt flat, well-drained bases with larger pile footprints.Restrict pile height to about 1.5 m to limit compaction and runoff channels.Avoid conical heaps to reduce edge drying and funnel drainage.Stabilize moisture by leaving piles for ~24 h before use.
Verification / Alternative check:
Ready-mix quality manuals and IS 2386 practices echo these measures to keep moisture predictable.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
all the above