The form work from the slabs excluding props, can be removed only after
1 day
4 days
7 days
14 days
Correct Answer:
4 days
← Previous Question
Next Question→
More Questions from
Building Construction
In soft clay of low bearing capacity, the type of steel pile generally used, is
The sound which continues even after its source is cut off, is called
The pile provided with one or more bulles in its vertical shaft, is generally known as
The steel pile which is generally sunk in soft clay or loose sand of low bearing capacity, is
The form work from the sides of beams can be removed only after
The concrete slump recommended for foundations, is
The stepped structure provided for lateral support of a structure, is
Open test pit is only suitable upto a depth of
To construct a 10 cm thick partition wall, you will prefer
The construction joints in buildings are provided after
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments