Project Scope Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Correct Answer: I Inputs Project scope statement Work breakdown structure WBS dictionary Project scope management plan Performance reports Approved change requests Work performance information II Tools and Techniques Change control system Variance analysis Replanning Configuration management system III Outputs Project scope statement(updates) Work breakdown structure(updates) WBS dictionary (updates) Scope baseline (updates) Requested changes Recommended corrective action Organizational process assets (updates) Project management plan (updates)