Correct Answer: I Inputs Enterprise environmental factors Organizational process assets Activity list Activity attributes Resource availability Project management plan II Tools and Techniques Expert Judgment Alternatives analysis Published estimating data Project management software Bottom-up estimating III Outputs Activity resource requirements Activity atributes (updates) Resource breakdown structure Resource calendars (updates) Requested changes