Home » Certification » PMP Certification

Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?

Correct Answer: I Inputs Enterprise environmental factors Organizational process assets Project scope statement Activity list Activity attributes Activity resource requirements Resource calendars Project management plan - Risk register - Activity cost estimates II Tools and Techniques Expert judgment Analogous estimating Parametric estimating Three-point estimates Reserve analysis III Outputs Activity duration estimates Activity attributes (updates)