Correct Answer: IInputs Project scope statement Activity list Activity attributes Milestone list Approved change requests II Tools and Techniques Precedence Diagramming Method (PDM) Arrow Diagramming Method (ADM) Schedule network templates Dependency determination Applying leads and lags III Outputs Project schedule network diagrams Activity list (updates) Activity attributes (updates) Requested changes