Correct Answer: 13 1 days 3
Explanation:
Work done by X in 8 days = | ❨ | 1 | x 8 | ❩ | = | 1 | . |
40 | 5 |
Remaining work = | ❨ | 1 - | 1 | ❩ | = | 4 | . |
5 | 5 |
Now, | 4 | work is done by Y in 16 days. |
5 |
Whole work will be done by Y in | ❨ | 16 x | 5 | ❩ | = 20 days. |
4 |
∴ X's 1 day's work = | 1 | , Y's 1 day's work = | 1 | . |
40 | 20 |
(X + Y)'s 1 day's work = | ❨ | 1 | + | 1 | ❩ | = | 3 | . |
40 | 20 | 40 |
Hence, X and Y will together complete the work in | ❨ | 40 | ❩ | = 13 | 1 | days. |
3 | 3 |