X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

Correct Answer: 13 1 days 3

Explanation:


Work done by X in 8 days = 1 x 8 = 1 .
40 5



Remaining work = 1 - 1 = 4 .
5 5



Now, 4 work is done by Y in 16 days.
5



Whole work will be done by Y in 16 x 5 = 20 days.
4



∴ X's 1 day's work = 1 , Y's 1 day's work = 1 .
40 20



(X + Y)'s 1 day's work = 1 + 1 = 3 .
40 20 40



Hence, X and Y will together complete the work in 40 = 13 1 days.
3 3