Home » Aptitude » Time and Work

A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished?

Correct Answer: 1:00 P.M.

Explanation:


(P + Q + R)'s 1 hour's work = 1 + 1 + 1 = 37 .
8 10 12 120



Work done by P, Q and R in 2 hours = 37 x 2 = 37 .
120 60



Remaining work = 1 - 37 = 23 .
60 60



(Q + R)'s 1 hour's work = 1 + 1 = 11 .
10 12 60



Now, 11 work is done by Q and R in 1 hour.
60



So, 23 work will be done by Q and R in 60 x 23 = 23 hours ≈ 2 hours.
60 11 60 11


So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.


← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion