Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

Correct Answer: 16

Explanation:

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.


Suppose Tanya takes x days to do the work.



5 : 4 :: 20 : x    ⟹ x = 4 x 20
5


x = 16 days.


Hence, Tanya takes 16 days to complete the work.