Difficulty: Easy
Correct Answer: 6 days
Explanation:
Problem restatement
With different solo times for A and B, B contributes for 10 days first. Compute the leftover work for A and the time needed.
Given data
Concept/Approach
Work done = rate × time. Remaining = 1 − (B's contribution).
Step-by-step calculation
Work by B in 10 days = 10 × (1/15) = 2/3 Remaining work = 1 − 2/3 = 1/3 Time for A = (1/3) ÷ (1/18) = 6 days
Verification
Equivalent unit method: LCM 90 units. B does 6 units/day × 10 = 60; remaining 30 units; A does 5/day → 6 days.
Common pitfalls
Final Answer
6 days
Discussion & Comments