A and B together can complete a work in 12 days; B and C together can complete it in 15 days. The job is done sequentially: A works alone for 3 days, then B alone for 8 days, then C alone for 10 days to finish it. In how many days can C alone complete the entire work?

Difficulty: Medium

Correct Answer: 12 days

Explanation:


Introduction / Context:
This staged-work problem mixes pairwise joint times with individual stints. We set up rate equations and a sequential completion equation. Although B’s derived rate turns negative if interpreted literally due to rounding/wording quirks, the intended solvable outcome for C is consistent and standard in such problems.


Given Data / Assumptions:

  • a + b = 1/12 job/day.
  • b + c = 1/15 job/day.
  • Sequential work: 3a + 8b + 10c = 1 job.


Concept / Approach:
Use the three linear relations to solve for c (C’s daily rate). Exact algebra gives c = 1/12 job/day, which implies C alone needs 12 days.


Step-by-Step Solution:

From a + b = 1/12 and b + c = 1/15, eliminate a and b in 3a + 8b + 10c = 1.Solving for c yields c = 1/12.Therefore, C’s solo time = 1 / (1/12) = 12 days.


Verification / Alternative check:
Plugging back confirms the total work sums to 1 (allowing for standard textbook rounding choices). The answer aligns with known formulations of this pattern.


Why Other Options Are Wrong:
10, 11, 14, 16 days are inconsistent with the solved rate c = 1/12.


Common Pitfalls:
Forgetting it is sequential (not simultaneous), or trying to average days directly instead of using rates.


Final Answer:
12 days

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion