Either 50 men or 80 women can finish a job in 50 days (equal total work). A contractor employs 40 men and 48 women. After every 10 days, 5 men and 8 women are removed, and this pattern continues until the job is completed. In how many days is the work finished?

Difficulty: Hard

Correct Answer: 50 days

Explanation:


Introduction / Context:
We are given equivalence: 50 men or 80 women in 50 days both complete the same 1 job. Compute per-man and per-woman daily rates, then evaluate work done in successive 10-day blocks as the crew shrinks.


Given Data / Assumptions:

  • Men-only plan: 50 men * 50 days = 1 job ⇒ man rate m = 1/2500 job/day.
  • Women-only plan: 80 women * 50 days = 1 job ⇒ woman rate w = 1/4000 job/day.
  • Initial crew: 40 men + 48 women; every 10 days remove 5 men and 8 women.


Concept / Approach:
Compute each 10-day block’s crew rate and cumulative work. Stop when cumulative work reaches 1 job.


Step-by-Step Solution:

Block 1 (days 1–10): 40m + 48w ⇒ rate = 40/2500 + 48/4000 = 0.028; work = 0.28.Block 2 (11–20): 35m + 40w ⇒ rate = 0.024; work = 0.24; cumulative = 0.52.Block 3 (21–30): 30m + 32w ⇒ rate = 0.020; work = 0.20; cumulative = 0.72.Block 4 (31–40): 25m + 24w ⇒ rate = 0.016; work = 0.16; cumulative = 0.88.Block 5 (41–50): 20m + 16w ⇒ rate = 0.012; work = 0.12; cumulative = 1.00.Total = 50 days.


Verification / Alternative check:
Later blocks (if continued) would overshoot; the job is exactly completed at day 50.


Why Other Options Are Wrong:
45/54/62/58 days mis-sum block outputs or assume constant crews.


Common Pitfalls:
Forgetting that both men and women reduce each cycle; failing to re-compute the rate per block.


Final Answer:
50 days

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion