A and B can do a piece of work in 45 days and 40 days, respectively. They start together, but A leaves after some days. B then completes the remaining work alone in 23 days. After how many days from the start did A leave?

Difficulty: Medium

Correct Answer: 9 days

Explanation:

Introduction / Context:We split the timeline into two phases: joint work for x days and then B alone for 23 days. Using constant daily rates simplifies the calculation.

Given Data / Assumptions:

  • A’s rate = 1/45 job/day.
  • B’s rate = 1/40 job/day.
  • Joint work for x days; B alone for 23 days; total work = 1 job.

Concept / Approach:Write the work sum: x*(1/45 + 1/40) + 23*(1/40) = 1. Solve for x.

Step-by-Step Solution:

1/45 + 1/40 = (8 + 9)/360 = 17/360.Equation: x*(17/360) + 23*(1/40) = 1.23/40 = 207/360 ⇒ x*(17/360) = 153/360 ⇒ x = 153/17 = 9 days.

Verification / Alternative check:Compute total: 9*(17/360) + 23/40 = 153/360 + 207/360 = 360/360 = 1 job; exact.

Why Other Options Are Wrong:7, 8, 10, 11 days would not satisfy the exact rate equation.

Common Pitfalls:Rounding fractions too early; mixing up who worked when.

Final Answer:9 days

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion