logo

CuriousTab

CuriousTab

Industrial Engineering and Production Management problems


  • 1. If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then break even point is equal to

  • Options
  • A.
  • B.
  • C.
  • D.
  • Discuss
  • 2. A critical activity has

  • Options
  • A. maximum slack
  • B. minimum slack
  • C. zero slack
  • D. average slack
  • Discuss
  • 3. A dummy activity in a net work diagram

  • Options
  • A. is represented by a dotted line
  • B. is an artificial activity
  • C. does not consume time or resources
  • D. all of these
  • Discuss
  • 4. In a thermal power plant, coal from the coal handling plant is moved to the boiler bunker through a

  • Options
  • A. belt conveyor
  • B. bucket conveyor
  • C. fork lift truck
  • D. overhead crane
  • Discuss
  • 5. In value engineering, important consideration is given to

  • Options
  • A. customer satisfaction
  • B. function concept
  • C. profit maximisation
  • D. cost reduction
  • Discuss
  • 6. When slack of an activity is positive

  • Options
  • A. it represents a situation where extra resources are available and the completion of project is not delayed
  • B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
  • C. the activity is critical and any delay in its performance will delay the completion of whole project
  • D. any one of the above
  • Discuss
  • 7. The essential condition for the decompression of an activity is that

  • Options
  • A. the project time should change due to decompression
  • B. after decompression the time of an activity invariably exceeds its normal time
  • C. an activity could be decompressed to the maximum extent of its normal time
  • D. none of the above
  • Discuss
  • 8. The unit cost in case of batch production is __________ as compared to jobbing production.

  • Options
  • A. same
  • B. low
  • C. high
  • Discuss
  • 9. Sampling method of determining standard time is profitable for long cycle operation.

  • Options
  • A. Correct
  • B. Incorrect
  • Discuss
  • 10. Break even analysis is a

  • Options
  • A. short term analysis
  • B. long term analysis
  • C. average of short and long term analysis
  • D. any one of these
  • Discuss

First 6 7 8 ... 11 .. 15 16 Last