CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Industrial Engineering and Production Management problems
1. Dispatching
Options
A. prescribes the sequence of operations to be followed
B. determines the programme for the operations
C. is concerned with the starting of processes
D. regulates the progress of job through various processes
Show Answer
Scratch Pad
Discuss
Correct Answer: is concerned with the starting of processes
2. String diagram is used
Options
A. for checking the relative values of various layouts
B. when a group of workers are working at a place
C. where processes require the operator to be moved from one work place to another
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: all of the above
3. Which of the following are the guidelines for the construction of a network diagram?
Options
A. Each activity is represented by one and only one arrow in the network.
B. Dangling must be avoided in a network diagram.
C. Dummy activity consumes no time or resource.
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: all of the above
4. Gantt chart is used for
Options
A. inventory control
B. material handling
C. production schedule
D. machine repair schedules
Show Answer
Scratch Pad
Discuss
Correct Answer: production schedule
5. In break even analysis, total cost consists of
Options
A. fixed cost + sales revenue
B. variable cost + sales revenue
C. fixed cost + variable cost
D. fixed cost + variable cost + profit
Show Answer
Scratch Pad
Discuss
Correct Answer: fixed cost + variable cost
6. A-B-C analysis is used in
Options
A. CPM
B. PERT
C. inventory control
D. all of these
Show Answer
Scratch Pad
Discuss
Correct Answer: inventory control
7. The probabilistic time is given by (where
t
o
= Optimistic time,
t
p
= Pessimistic time, and
t
n
= Most likely time)
Options
A.
B.
C.
D.
Show Answer
Scratch Pad
Discuss
Correct Answer:
8. PERT requires
Options
A. single time estimate
B. double time estimate
C. triple time estimate
D. none of these
Show Answer
Scratch Pad
Discuss
Correct Answer: triple time estimate
9. Linear programming model can be applied to line balancing problem and transportation problem.
Options
A. True
B. False
Show Answer
Scratch Pad
Discuss
Correct Answer: True
10. When slack of an activity is negative
Options
A. it represents a situation where extra resources are available and the completion of project is not delayed
B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. the activity is critical and any delay in its performance will delay the completion of whole project
D. all of the above
Show Answer
Scratch Pad
Discuss
Correct Answer: it represents that a programme falls behind schedule and additional resources are required to complete the project in time
First
5
6
7
...
11
..
15
16
Last
More in Mechanical Engineering:
Automobile Engineering
Compressors, Gas Dynamics and Gas Turbines
Engineering Materials
Engineering Mechanics
Heat Transfer, Refrigeration and Air Conditioning
Hydraulic Machines
Hydraulics and Fluid Mechanics
IC Engines and Nuclear Power Plants
Industrial Engineering and Production Management
Machine Design
Production Engineering
Steam Boilers and Engines
Steam Nozzles and Turbines
Strength of Materials
Theory of machines
Thermodynamics
Workshop Technology