CuriousTab
Search
CuriousTab
Home
Aptitude
Computer
C Programming
C# Programming
C++ Programming
Database
Java Programming
Networking
Engineering
Biochemical Engineering
Biochemistry
Biotechnology
Chemical Engineering
Civil Engineering
Computer Science
Digital Electronics
Electrical Engineering
Electronics
Electronics and Communication Engineering
Mechanical Engineering
Microbiology
Technical Drawing
GK
Current Affairs
General Knowledge
Reasoning
Data Interpretation
Logical Reasoning
Non Verbal Reasoning
Verbal Ability
Verbal Reasoning
Exams
AIEEE
Bank Exams
CAT
GATE
IIT JEE
TOEFL
Jobs
Analyst
Bank PO
Database Administrator
IT Trainer
Network Engineer
Project Manager
Software Architect
Tunnelling problems
1. In the given figure drill holes, heading, mucking and benching are mumbered as 1, 2, 3, 4 The correct sequence is :
Options
A. 4 1 2 3
B. 1 2 3 4
C. 4 1 3 2
D. 3 4 1 3
Show Answer
Scratch Pad
Discuss
Correct Answer: 4 1 3 2
2. The advantages of providing a pair of tunnels as compared to only one large highway tunnel is :
Options
A. economy in cost of construction
B. avoidance of head on collisions
C. provision of separate exit and entrance of two traffic streams
D. facility in carrying out repairs
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
3. For full face method, the excavation to be done is generally divided into
Options
A. two sections
B. three sections
C. four sections
D. five sections.
Show Answer
Scratch Pad
Discuss
Correct Answer: three sections
4. The concentration of the dust particles of the size 0.5 to 5 microns adjacent to the working face should not be more than
Options
A. 200 particles/cm
3
B. 250 particles/cm
3
C. 300 particles/cm
3
D. 450 particles/cm
3
E. 400 particles/cm
3
Show Answer
Scratch Pad
Discuss
Correct Answer: 450 particles/cm
3
5. A tunnel is found more advantageous as compared to the alternate routes because it:
Options
A. remains free from snow
B. reduces the cost by reducing the route distance
C. reduces the maintenance cost
D. avoids interference with surface rights
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
6. In case of railways,
Options
A. a detour round the hill is preferred
B. a open cut is preferred
C. tunnelling is preferred
D. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: tunnelling is preferred
7. The following operations are required for tunnelling in rocky terrain :
1. Removing the foul gases
2. Marking the tunnel profile
3. Setting up and drilling
4. Checking misfire
5. Mucking
The correct sequence is :
Options
A. 1 2 3 4 5
B. 2 3 5 4 1
C. 4 2 1 3 5
D. 2 3 1 4 5
Show Answer
Scratch Pad
Discuss
Correct Answer: 2 3 1 4 5
8. Pick up the correct statement from the following:
Options
A. The topographical maps of the Survey of India are useful in the mountainous region for tunnelling.
B. The height point on the ridge is fixed with the help of reciprocal ranging
C. The accuracy of 1 in 10, 000 is required for planimetric control
D. 1 second theodolite is used for angular measurement to achieve an angular error of 15
N
where
N
is number of angles
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
9. Which one of the following methods is adopted for permanent drainage of tunnels :
Options
A. provision of longitudinal drains
B. continuous open drains
C. concrete lining
D. grouting with cement or chemicals
E. All the above.
Show Answer
Scratch Pad
Discuss
Correct Answer: All the above.
10. For B.G. single track, the section of the tunnel must have a width
Options
A. 4.2 m to 4.5 m
B. 4.5 m to 4.8 m
C. 4.9 m to 5.5 m
D. 5.5 m to 5.8 m
Show Answer
Scratch Pad
Discuss
Correct Answer: 4.9 m to 5.5 m
First
2
3
4
5
More in Civil Engineering:
Advanced Surveying
Airport Engineering
Applied Mechanics
Building Construction
Building Materials
Concrete Technology
Construction Management
Docks and Harbours
Elements of Remote Sensing
Engineering Economy
Estimating and Costing
GATE Exam Questions
Highway Engineering
Hydraulics
Irrigation
Railways
RCC Structures Design
SI Units
Soil Mechanics and Foundation Engineering
Steel Structure Design
Strength of Materials
Structural Design Specifications
Surveying
Theory of Structures
Tunnelling
UPSC Civil Service Exam Questions
Waste Water Engineering
Water Resources Engineering
Water Supply Engineering