Construction Management problems


  • 1. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is

  • Options
  • A. (t1 - t2) - t
  • B. t - (t1 - t2)
  • C. (t1 + t2) - t
  • D. t + (t1 - t2)
  • Discuss
  • 2. While scheduling a project by C.P.M.

  • Options
  • A. a project is divided into various activities
  • B. required time for each activity is established
  • C. sequence of various activities is made according to their importance
  • D. net work is drawn by connecting the activities and the events
  • E. All the above.
  • Discuss
  • 3. Power stations are generally treated as

  • Options
  • A. light construction
  • B. heavy construction
  • C. industrial construction
  • D. electrical construction.
  • Discuss