Construction Management problems


  • 1. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

  • Options
  • A. started 5 days later
  • B. completed 5 days later
  • C. performed at slower rate in 15 days
  • D. all the above.
  • Discuss
  • 2. Frederick W. Taylor introduced a system of working known as

  • Options
  • A. line organisation
  • B. line and staff organisation
  • C. functional organisation
  • D. effective organisation.
  • Discuss
  • 3. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

  • Options
  • A.
  • B.
  • C.
  • D.
  • Discuss
  • 4. The technique for establishing and maintaining priorities among the various jobs of a project, is known

  • Options
  • A. Event flow scheduling technique
  • B. Critical ratio scheduling
  • C. Slotting technique for scheduling
  • D. Short interval scheduling.
  • Discuss
  • 5. Pick up the correct statement from the following:

  • Options
  • A. CPM analysis is activity oriented
  • B. PERT analysis is event oriented
  • C. CPM does not make any allowance for the uncertainties in the duration of time
  • D. In CPM, the time is related to cost
  • E. All the above.
  • Discuss
  • 6. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to

  • Options
  • A. LST-EST
  • B. LFT-EFT
  • C. TL-EFT
  • D. all the above.
  • Discuss
  • 7. Works costing less than Rs. 20,000 are treated as

  • Options
  • A. projects
  • B. major projects
  • C. minor projects
  • D. all the above.
  • Discuss
  • 8. Various activities of a project, are shown on bar charts by

  • Options
  • A. vertical lines
  • B. horizontal lines
  • C. dots
  • D. crosses.
  • Discuss
  • 9. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

  • Options
  • A. duration
  • B. total flat
  • C. free float
  • D. interfering float.
  • Discuss
  • 10. Final technical authority of a project lies with

  • Options
  • A. Assistant Engineer
  • B. Executive Engineer
  • C. Superintending Engineer
  • D. Chief Engineer.
  • Discuss