Network diagrams (CPM/PERT): basic construction guidelines Consider standard rules for drawing activity-on-arrow networks. Identify the set of correct guidelines.

Difficulty: Easy

Correct Answer: All of the above

Explanation:


Guidelines explained
• One arrow per activity avoids duplication and ambiguity.• Avoid dangling ends; every activity must start/end at well-defined events.• Dummy activities exist only to maintain logic; they have zero duration and no resource use.


Final Answer
All of the above.