Network diagrams (CPM/PERT): basic construction guidelines Consider standard rules for drawing activity-on-arrow networks. Identify the set of correct guidelines.

Mechanical Engineering Industrial Engineering and Production Management Difficulty: Easy
Choose an option
  • A
    Each activity is represented by one and only one arrow in the network
  • B
    Dangling (unconnected ends) must be avoided in the network diagram
  • C
    A dummy activity consumes no time and no resources
  • D
    All of the above

Answer

Correct Answer: All of the above

Explanation

Guidelines explained• One arrow per activity avoids duplication and ambiguity.• Avoid dangling ends; every activity must start/end at well-defined events.• Dummy activities exist only to maintain logic; they have zero duration and no resource use.

Final AnswerAll of the above.