Scheduling tools: primary use of a Gantt (bar) chart in production Identify the most appropriate application area of Gantt charts in operations management. Choose the best option.

Difficulty: Easy

Correct Answer: Production scheduling and tracking

Explanation:


Concept
Gantt (bar) charts provide a time-scaled visual of planned vs. actual start/finish for jobs, machines, or departments. They are widely used for production schedules and progress control.


Why others are less appropriate
Inventory control uses ABC/EOQ etc.; material handling uses different tools. Maintenance can use Gantt, but its primary association in operations is production scheduling.


Final Answer
Production scheduling and tracking.

More Questions from Industrial Engineering and Production Management

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion