Engineering change control (ECC): In a production environment, the engineering change control system primarily updates which planning artifact when a design or method change must be implemented?

Difficulty: Medium

Correct Answer: production schedule

Explanation:


Introduction / Context:
Engineering Change Control (ECC) ensures that design revisions, method changes, and part substitutions are introduced in a controlled manner. A key question is which planning artifact must be updated first to reflect the approved change and prevent nonconforming production.


Given Data / Assumptions:

  • An approved engineering change affects how and when items are produced.
  • Shop-floor orders and plans must shift to respect the “effective-from” date or serial number range of the change.
  • We are asked for the primary planning artifact updated to drive execution.


Concept / Approach:
While routing/operations files may also be revised, the production schedule is the execution driver that determines which orders run and when. Updating the schedule ensures the correct revision is produced at the right time and prevents using obsolete instructions. The schedule propagates the change to work orders, materials staging, and capacity plans.


Step-by-Step Solution:
Recognize ECC as a controlled release of changes with an effective date/point.Identify the artifact that aligns orders with the new revision: the production schedule.Acknowledge that operations files may be revised, but the schedule operationalizes the change.


Verification / Alternative check:
In MRP/MES practice, engineering change notices are tied to effectivity in the master data and are reflected via rescheduling or firming orders to match new revisions.


Why Other Options Are Wrong:

  • Operations file: Often updated, but without schedule alignment, changes may not be executed correctly.
  • Work force demographic data: Not typically affected by an engineering change.
  • All/None: Over- or under-inclusive for the primary driver of execution.


Common Pitfalls:
Updating documentation without rescheduling orders; this creates mismatches between planned and actual build revisions.


Final Answer:
production schedule

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion