A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in?

Correct Answer: 5 days

Explanation:

B's 9 day's work = 9 x (1/12) = 3/4
Remaining work = (1 - 3/4) = 1/4
1/4 work is done by A in = 20 x (1/4) = 5 days.