Difficulty: Easy
Correct Answer: 3 days
Explanation:
Introduction / Context:
This problem reinforces the core Time-and-Work principle that individual work rates add when people work together. We convert each person’s completion time into a daily rate (jobs per day), add the rates, and take the reciprocal to get the total time.
Given Data / Assumptions:
Concept / Approach:
For one complete job, total time T equals 1 divided by the combined rate R. That is, T = 1 / (rate_A + rate_B). Always add rates, not times, when tasks are done simultaneously.
Step-by-Step Solution:
rate_A = 1/4rate_B = 1/12Combined rate R = 1/4 + 1/12 = 3/12 + 1/12 = 4/12 = 1/3 job/dayTime T = 1 / (1/3) = 3 days
Verification / Alternative check:
In 3 days, A would complete 3 * (1/4) = 3/4 of the job and B would complete 3 * (1/12) = 1/4 of the job. Total = 3/4 + 1/4 = 1 job, confirming correctness.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
3 days
Discussion & Comments