Difficulty: Medium
Correct Answer: 9 3/8 days
Explanation:
Introduction / Context: This problem gives partial completion benchmarks. Convert each to a full-job time or directly to daily rates, then add to get the joint rate and invert for total time.
Given Data / Assumptions:
Concept / Approach: Combined daily rate r = r(A) + r(B) = 1/15 + 1/25. Total time = 1 / r.
Step-by-Step Solution: 1/15 + 1/25 = (5 + 3)/75 = 8/75. Total time = 1 / (8/75) = 75/8 = 9.375 days = 9 3/8 days.
Verification / Alternative check: Decimal verification: 9.375 * (8/75) = 1, so the calculation is exact.
Why Other Options Are Wrong: 7 3/4, 8 4/5, 10 days do not match the sum-of-rates inversion; 9 days is close but not exact.
Common Pitfalls: Treating partial-job times as direct times instead of converting to rates; missing fraction simplifications.
Final Answer: 9 3/8 days
Discussion & Comments