A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved.
26, 000 m3
26, 500 m3
27, 000 m3
27, 500 m3
Correct Answer:
27, 500 m3
← Previous Question
Next Question→
More Questions from
Estimating and Costing
As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken
The main factor to be considered while preparing a detailed estimate, is
The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as
Brick walls are measured in sq. m if the thickness of the wall is
The cross-sections for a highway is taken at
The plinth area of a building not includes
The height of the sink of wash basin above floor level is kept
In case of laying gullies, siphons, intercepting traps, the cost includes
The concrete work for the following part of the building of specified thickness is measured in square metres
Cost of fittings and their fixing is specified for the following sanitary fittings
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments