Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
Options
A. 1. Pouring of Concrete 2. Erection of form work 3. Curing of concrete 4. Removal of form work
B. 1. Erection of form work 2. Pouring of concrete 3. Curing of concrete 4. Removal of form work
C. 1. Removal of form work 2. Erection of form work 3. Pouring of concrete 4. Curing of concrete
D. 1. Pouring of concrete 2. Curing of concrete 3. Erection of form work 4. Removal of form work
Correct Answer
1. Erection of form work 2. Pouring of concrete 3. Curing of concrete 4. Removal of form work
Construction Management problems
Search Results
1. Critical Path Net Work helps an engineer
Options
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
10. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good