  • Question
  • 36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?


  • Options
  • A. 12
  • B. 18
  • C. 22
  • D. 24
  • E. None of these

  • Correct Answer
  • 24 

    Explanation
    Let the required number of days be x

    Less men, More days (Indirect Proportion)

    ∴ 27 : 36 :: 18 : x    ⟺    27 x x = 36 x 18

    x = 36 x 18
    27

    x = 24.


  • Chain Rule problems


    Search Results


    • 1. In a dairy farm, 40 cows eat 40 bags of husk in 40 days. In how many days one cow will eat one bag of husk?

    • Options
    • A. 1
    • B. 1140
    • C. 40
    • D. 80
    • Discuss
    • 2. 
      If x = 3 + 2√2, then the value of x - 1 is:
      x

    • Options
    • A. 1
    • B. 2
    • C. 2√2
    • D. 3√3
    • Discuss
    • 3. (17)3.5 x (17)? = 178

    • Options
    • A. 2.29
    • B. 2.75
    • C. 4.25
    • D. 4.5
    • Discuss
    • 4. (0.04)-1.5 =?

    • Options
    • A. 25
    • B. 125
    • C. 250
    • D. 625
    • Discuss
    • 5. (256)0.16 x (256)0.09 =?

    • Options
    • A. 4
    • B. 16
    • C. 64
    • D. 256.25
    • Discuss
    • 6. 3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

    • Options
    • A. 9
    • B. 10
    • C. 11
    • D. 12
    • Discuss
    • 7. 4 mat-weavers can weave 4 mats in 4 days. At the same rate, how many mats would be woven by 8 mat-weavers in 8 days?

    • Options
    • A. 4
    • B. 8
    • C. 12
    • D. 16
    • Discuss
    • 8. A flagstaff 17.5 m high casts a shadow of length 40.25 m. The height of the building, which casts a shadow of length 28.75 m under similar conditions will be:

    • Options
    • A. 10 m
    • B. 12.5 m
    • C. 17.5 m
    • D. 21.25 m
    • Discuss
    • 9. An industrial loom weaves 0.128 metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metres of cloth?

    • Options
    • A. 178
    • B. 195
    • C. 204
    • D. 488
    • Discuss
    • 10. If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in how many days?

    • Options
    • A. 1
    • B. 72
    • C. 7
    • D. 49
    • Discuss


    Comments

    There are no comments.

Enter a new Comment