Answers A, B and D all result from effectively integrating the work of the project management process groups. PMBOK [4.0]
Answer A is incorect because it is not a correct statement and has nothing to do with ambiguous jurisdiction. Answer C is incorrect because ambiguous jurisdiction is not related to legal issues at a company. Answer D is incorrect because the statement is incorrect and is not related to ambiguous jurisdiction.
?Sensitivity analysis helps to determine which risks have the most potential impact on the project.?
Answer A is incorrect because the WBS hierarchy does not prevent duplication by itself. Answer C is incorrect because a WBS is focused on deliverables and components or work packages and not on tasks. Answer D is incorrect because a WBS can be sized appropriately to the project size with as many levels as necessary.
There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]
Key elements in the procurement management plan are enumerated in this PMBOK section. [12.1.3.1]
Answer A is reversed. Answer C is sometimes mistakenly used to forecast project completion (it?s invalid because it does not take into consideration which completed tasks are on the critical path). Answer D is the definition of Schedule Variance.
?Verify Scope is the process of formalizing acceptance of the completed project deliverables. Verifying scope includes reviewing deliverables with the customer or sponsor to ensure that they are completed satisfactorily and obtaining formal acceptance of deliverables by the customer or sponsor.? PMBOK [5.4]
Answers B and C belong to quality management, and answer D was formulated by Elizabeth Duffy and suggested that we all try to adjust our lives so that we have a dynamic balance (homeostasis) between challenge and relaxation. Kerstner, Chapter 18