logo

CuriousTab

CuriousTab

Discussion


Home Aptitude Time and Work Comments

  • Question
  • 12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?


  • Options
  • A. 2 days
  • B. 2.5 days
  • C. 2.25 days
  • D. 3 days

  • Correct Answer
  • 2.25 days 

    Explanation

    1 man's 1 day work = 1/108
    12 men's 6 day's work = 1/9 x 6 = 2/3

    Remaining work = 1 - 2/3 = 1/3

    16 men's 1 day work = 1/108 x 16 = 4/27
    4/27 work is done by them in 1 day.

    1/3 work is done by them in 27/4 x 1/3 = 9/4 days.

  • Tags: AIEEE, Bank Exams, CAT, GATE, Bank Clerk, Bank PO

    Time and Work problems


    Search Results


    • 1. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it ?

    • Options
    • A. 40 days
    • B. 36 days
    • C. 32 days
    • D. 34 days
    • Discuss
    • 2. 6 men can complete a piece of work in 12 days. 8 women can complete the same piece of work in 18 days whereas 18 children can complete the piece of work in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men were to complete the remaining work in 1 day how many men would be required totally?

    • Options
    • A. 38
    • B. 72
    • C. 36
    • D. 76
    • Discuss
    • 3. If 10 men take 15 days to complete a work. In how many days will 37 men complete the work?

    • Options
    • A. 3 days
    • B. 4 days
    • C. 5 days
    • D. 6 days
    • Discuss
    • 4. After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?

    • Options
    • A. 24.5 days
    • B. 26.6 days
    • C. 25 days
    • D. 20 days
    • Discuss
    • 5. P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

    • Options
    • A. 56 days
    • B. 54 days
    • C. 60 days
    • D. 64 days
    • Discuss
    • 6. M can complete a piece of work in 10 days. N is 33.33% less efficient than M. calculate the number of days required to both to complete the work?

    • Options
    • A. 6 days
    • B. 8 days
    • C. 11 days
    • D. 13 days
    • Discuss
    • 7. Four pipes P,Q, R and S can fill a cistern in 20,25, 40 and 50 hours respectively.The first pipe P was opened at 6:00 am, Q at 8:00 am, R at 9:00 am and S at 10:00 am. when will the Cistern be full?

    • Options
    • A. 4:18 pm
    • B. 3:09 pm
    • C. 12:15 pm
    • D. 11:09 am
    • Discuss
    • 8. P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

    • Options
    • A. 16 days
    • B. 13 days
    • C. 15 days
    • D. 12 days
    • Discuss
    • 9. 9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?

    • Options
    • A. 15 days
    • B. 11 days
    • C. 14 days
    • D. 12 days
    • Discuss
    • 10. A contractor undertake to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?

    • Options
    • A. 64
    • B. 62
    • C. 58
    • D. 56
    • Discuss


    Comments

    There are no comments.

Enter a new Comment