9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?

Correct Answer: 12 days

Explanation:

9M + 12B ----- 12 days ...........(1)
12M + 12B ------- 10 days........(2)
10M + 10B -------?
108M + 144B = 120M +120B
24B = 12M => 1M = 2B............(3)


From (1) & (3)


18B + 12B = 30B ---- 12 days


20B + 10B = 30B -----? => 12 days.