M can complete a piece of work in 10 days. N is 33.33% less efficient than M. calculate the number of days required to both to complete the work?

Correct Answer: 6 days

Explanation:

M = 10 days


The ratio of efficiency of M & N are 3 : 2


Hence, the time rquired for N alone = 15 days


=> Required time taken t=by both to complete the work = M x N / M + N 


= 10 x 15/ 10 + 15


= 150/25


= 6 days.