Correct Answer: 2 days
Explanation:
Total work = 100+50 = 150man-days
In 8 days 100 man-days work has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.
Discussion & Comments