Dead storage allowance in reservoir capacity Dead storage (reserved for silt deposition over project life) is generally taken as what fraction of the total capacity Q?

Civil Engineering Water Supply Engineering Difficulty: Easy
Choose an option
  • A
    1/8 of Q
  • B
    1/6 of Q
  • C
    1/5 of Q
  • D
    1/4 of Q
  • E
    1/3 of Q

Answer

Correct Answer: 1/3 of Q

Explanation

Introduction / Context:Reservoir capacity is divided into dead storage (below outlets) and live/active storage. Dead storage often includes allowance for silt deposition during the design life so that active storage is preserved as long as possible.

Given Data / Assumptions:

  • General planning guidance; actual projects calibrate with sediment yield studies.
  • Design life where significant siltation is expected.

Concept / Approach:Textbook and exam practice frequently take a dead-storage allowance on the order of about one-third of total for preliminary sizing in silt-laden rivers, subject to later refinement. This ensures intake function and maintains live storage for much of the project life.

Step-by-Step Solution:Relate dead storage to projected sediment volume over life.Select the commonly adopted preliminary fraction ≈ 1/3 Q when no site-specific study is given.

Verification / Alternative check:More detailed designs use trap efficiency curves and catchment sediment yield to refine the fraction, but 1/3 Q remains a standard exam value.

Why Other Options Are Wrong:

  • Fractions 1/8 to 1/4 may under-allow silt in high-sediment basins for preliminary design.

Common Pitfalls:Using a rule-of-thumb instead of a sedimentation study at DPR stage; omitting dead-storage elevation relative to intakes.

Final Answer:1/3 of Q

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion