Difficulty: Easy
Correct Answer: c, d, e, a, b
Explanation:
Introduction / Context:Construction follows a structural-to-finish sequence to ensure safety and quality.
Given Data / Assumptions:Foundation supports walls; ceiling/roofing comes after walls; plaster precedes painting.
Concept / Approach:Arrange by prerequisite: structure → enclosure → finishing.
Step-by-Step Solution:Foundation (c).Walls (d).Ceiling (e).Plastering (a).Painting (b).
Verification / Alternative check:Site schedules and method statements reflect this order.
Why Other Options Are Wrong:Painting cannot precede plastering; walls must exist before ceilings in most builds.
Common Pitfalls:Ignoring drying/curing times between plastering and painting; though not listed, the order still holds.
Final Answer:c, d, e, a, b