Difficulty: Easy
Correct Answer: c, d, e, a, b
Explanation:
Introduction / Context:
Construction follows a structural-to-finish sequence to ensure safety and quality.
Given Data / Assumptions:
Foundation supports walls; ceiling/roofing comes after walls; plaster precedes painting.
Concept / Approach:
Arrange by prerequisite: structure → enclosure → finishing.
Step-by-Step Solution:
Foundation (c).Walls (d).Ceiling (e).Plastering (a).Painting (b).
Verification / Alternative check:
Site schedules and method statements reflect this order.
Why Other Options Are Wrong:
Painting cannot precede plastering; walls must exist before ceilings in most builds.
Common Pitfalls:
Ignoring drying/curing times between plastering and painting; though not listed, the order still holds.
Final Answer:
c, d, e, a, b
Discussion & Comments