Arrange building activities from foundation to finishing. a) Plastering b) Painting c) Foundation d) Wallse) Ceiling

Verbal Reasoning Logical Sequence of Words Difficulty: Easy
Choose an option
  • A
    a, b, c, d, e
  • B
    c, d, a, b, e
  • C
    c, d, e, a, b
  • D
    e, d, c, b, a
  • E
    c, e, d, a, b

Answer

Correct Answer: c, d, e, a, b

Explanation

Introduction / Context:Construction follows a structural-to-finish sequence to ensure safety and quality.

Given Data / Assumptions:Foundation supports walls; ceiling/roofing comes after walls; plaster precedes painting.

Concept / Approach:Arrange by prerequisite: structure → enclosure → finishing.

Step-by-Step Solution:Foundation (c).Walls (d).Ceiling (e).Plastering (a).Painting (b).

Verification / Alternative check:Site schedules and method statements reflect this order.

Why Other Options Are Wrong:Painting cannot precede plastering; walls must exist before ceilings in most builds.

Common Pitfalls:Ignoring drying/curing times between plastering and painting; though not listed, the order still holds.

Final Answer:c, d, e, a, b