Arrange building activities from foundation to finishing. a) Plastering b) Painting c) Foundation d) Wallse) Ceiling

Difficulty: Easy

Correct Answer: c, d, e, a, b

Explanation:


Introduction / Context:
Construction follows a structural-to-finish sequence to ensure safety and quality.



Given Data / Assumptions:
Foundation supports walls; ceiling/roofing comes after walls; plaster precedes painting.



Concept / Approach:
Arrange by prerequisite: structure → enclosure → finishing.



Step-by-Step Solution:
Foundation (c).Walls (d).Ceiling (e).Plastering (a).Painting (b).



Verification / Alternative check:
Site schedules and method statements reflect this order.



Why Other Options Are Wrong:
Painting cannot precede plastering; walls must exist before ceilings in most builds.



Common Pitfalls:
Ignoring drying/curing times between plastering and painting; though not listed, the order still holds.



Final Answer:
c, d, e, a, b

More Questions from Logical Sequence of Words

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion