Difficulty: Easy
Correct Answer: All of these
Explanation:
Introduction / Context:
Cost estimates serve many critical roles across the project life cycle, from tendering to negotiation and control. A well-prepared estimate enables contractors to price competitively, justify rates, and manage financial risk. This question checks whether you recognize the breadth of uses of an estimate in construction contracts, including lump-sum and unit-rate arrangements as well as negotiation of definitive budgets.
Given Data / Assumptions:
Concept / Approach:
For a lump-sum bid, the estimate aggregates quantities, productivity, and pricing to arrive at one competitive price. For unit-price contracts, the estimate underpins itemwise rates based on measured quantities. During negotiations, a definitive estimate—typically with higher accuracy and detailed backing—supports scope clarification, risk allowances, and schedule-cost alignment.
Step-by-Step Solution:
Verification / Alternative check:
Standard estimating practice recognizes conceptual, preliminary, and definitive estimates; all feed into different contracting strategies. Both lump-sum and unit-rate bids are fundamentally derived from the contractor's internal estimate.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
All of these
Discussion & Comments