Within cost accounting for construction projects, which of the following are standard elements of cost recognized in job costing and estimate build-ups?

Difficulty: Easy

Correct Answer: All of these

Explanation:


Introduction / Context:
Breaking down project costs into elements clarifies pricing, control, and reporting. Standard cost elements include direct material (consumables and permanent works), direct labour (on-site workforce), and overheads (indirect costs such as supervision and site facilities). Recognizing all three ensures complete capture of project expenditure.


Given Data / Assumptions:

  • Direct materials: cement, steel, aggregates, fixtures, etc.
  • Direct labour: masons, carpenters, operators, helpers.
  • Overheads: plant, temporary works, supervision, insurance, utilities.


Concept / Approach:

Estimates and cost codes are structured so each pay item’s unit rate is the sum of material, labour, equipment/overhead, and markups. Omitting any element underprices the job and undermines cost control.


Step-by-Step Solution:

Identify cost buckets: materials, labour, overheads (including equipment).Confirm that each is necessary to perform the work.Hence, all listed options are valid → choose 'All of these'.


Verification / Alternative check:

Standard estimating manuals and WBS structures show these elements explicitly in rate build-ups and earned value tracking.


Why Other Options Are Wrong:

  • Choosing any single element ignores the rest of the real project costs.
  • 'None of these' is contrary to basic cost accounting.


Common Pitfalls:

  • Misclassifying site overheads as general overheads, leading to under-recovery.
  • Excluding wastage and productivity losses from direct cost calculations.


Final Answer:

All of these

More Questions from Engineering Economy

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion