Difficulty: Easy
Correct Answer: All of these
Explanation:
Introduction / Context:
Breaking down project costs into elements clarifies pricing, control, and reporting. Standard cost elements include direct material (consumables and permanent works), direct labour (on-site workforce), and overheads (indirect costs such as supervision and site facilities). Recognizing all three ensures complete capture of project expenditure.
Given Data / Assumptions:
Concept / Approach:
Estimates and cost codes are structured so each pay item’s unit rate is the sum of material, labour, equipment/overhead, and markups. Omitting any element underprices the job and undermines cost control.
Step-by-Step Solution:
Verification / Alternative check:
Standard estimating manuals and WBS structures show these elements explicitly in rate build-ups and earned value tracking.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
All of these
Discussion & Comments