Correct Answer: I Inputs Enterprise environmental factors Organizational process assets Project scope statement Work breakdown structure WBS dictionary Project management plan - Risk register - Risk - related contractual agreements - Resource requirements - Project schedule - Activity cost estimates - Cost baseline II Tools and Techniques Make-or-buy analysis Expert judgement Contract types III Outputs Procurement management plan contract statement of work make-or-buy decisions Requested changes