Home » Aptitude » Time and Work

A and B can complete a work together in 30 days. They work together for 20 days; then B leaves, and A finishes the remaining work in the next 20 days. In how many days can A alone finish the work?

Difficulty: Medium

Correct Answer: 60 days

Explanation:

Problem restatement
The pair completes a project in 30 days. After 20 days of working together, B leaves; A alone completes the rest in 20 days. Find A's solo time.


Given data

  • (A + B) time = 30 days ⇒ (A + B) rate = 1÷30 per day.
  • First phase: 20 days together.
  • Second phase: 20 days by A alone.

Concept/Approach
Compute the fraction completed in phase 1; the remainder is done by A in phase 2, which gives A's rate.


Step-by-step calculation
Work done in first 20 days = 20 × (1÷30) = 2÷3Remaining work = 1 − 2÷3 = 1÷3A completes 1÷3 in 20 days ⇒ A's rate = (1÷3) ÷ 20 = 1÷60 per dayTherefore, A's time alone = 60 days


Verification/Alternative
Check units: rate in job/day times days gives fraction of job, consistent in both phases.


Common pitfalls
Forgetting that only A works in the last 20 days; mixing average of 30 and 20 without using rates is incorrect.


Final Answer
60 days

← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion